Transbay Transit Center Project - Construction Activities Update

The TransBay Transit Center has published this new 10-day look ahead:

10 Day Look Ahead: Construction Activities

Friday, March 29, 2013 – Sunday, April 7, 2013

NOTICE - FULL STREET CLOSURE - BEALE STREET BRIDGE ( BETWEEN MISSION & HOWARD STREETS), APRIL 5-8

WEATHER CONTINGENCY DATE, APRIL 12-15

Beale Street will be closed April 5-8, to install the third and final traffic bridge on Beale Street, between Mission and Howard Streets.

Beale Street will be closed to through traffic and pedestrians beginning Friday at 7:00 PM and will reopen Monday at 5:00 AM.

This week at Transbay...

What to Expect This Weekend (3/30/13 – 3/31/13):

Eastern Transit Center Site (Between Beale and Fremont Streets): This weekend there is no construction work scheduled for Saturday, March 30 or Sunday, March 31.

Central Transit Center Site (Between First and Fremont Streets): This weekend there is no construction work scheduled for Saturday, March 30 or Sunday, March 31.

Western Transit Center Site (Between Second and First Streets): This weekend there is no construction work scheduled for Saturday, March 30 or Sunday, March 31.

Weekday Work (Monday 4/1/13 - Friday 4/5/13):

Night Shift:

Excavation and Internal Bracing Work:

Beale Street (Between Mission and Howard Streets): There will be bridge preparation work Monday through Friday with work scheduled from 6:00 AM to 11:30 PM. The Beale Street temporary bridge preparation has resulted in construction impacts with traffic lanes reduced from three lanes down to two until mid April 2013. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gate to Beale Street.

Eastern Transit Center Site (Between Fremont and Beale Streets):​ There will be construction access trestle preparation work Monday through Friday with work scheduled from 6:00 AM to 11:30 PM with excavation and trucking Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located on Fremont Street and exit the construction gate at Beale Street.

Central Transit Center Site (Between First and Fremont Streets): This week excavation and trucking is scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Welding of trestle steel and cross lot steel bracing scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Western Transit Center Site (Between Second and First Streets): This week excavation and trucking is scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Welding of trestle steel and cross lot steel bracing scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located on Howard Street (between First and Second Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Day Shift:

Excavation and Bracing/Below Grade Transit Center Construction:

The project's internal steel bracing, excavation and trucking of soils has become a 24 hour activity with excavation down to an average depth of 60 to 65 feet. The excavation progresses from the west transit center site to the eastern end for the new Transbay Transit Center building and will continue through the end of 2014. The western zone excavation and bracing is in progress with a target completion of mid 2013, the below grade contractor will soon start construction of the lower level concrete foundation. The central Transit Center Site internal steel bracing, excavation and trucking of soils is in progress and continues until the end of 2013. The eastern Transit Center Site construction access trestle, excavation and trucking of soils have commenced and will continue into early 2014.

Beale Street (Between Mission and Howard Streets): There will be bridge preparation on the east side will work day and night Monday through Friday with work scheduled from 6:00 AM to 11:30 PM. Some demolition of the surface level concrete will be performed this week during the day shift. The Beale Street temporary bridge preparation has resulted in construction impacts with traffic lanes reduced from three down to two lanes until early April 2013. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gates.

Eastern Transit Center Site (Between Beale and Fremont Streets): This week the drilled piers are being installed for future construction of the access trestle and to support excavation and bracing. Some demolition of the surface level concrete slab will be performed during the day shift resulting in vibration and noise. Trucks will enter from the construction gate located on Fremont Street (between Mission and Howard Streets) and exit the construction gate at Beale Street.

Central Transit Center Site (Between First and Fremont Streets): This week excavation and trucking is scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Welding of trestle steel and cross lot steel bracing scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Western Transit Center Site (Between Second and First Streets): This week excavation and trucking is scheduled from Monday through Friday between the hours of 6:00 AM to 11:30 PM. Trucks will enter from the construction gate located on Howard Street (between First and Second Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Underground Utilities/Trenching Work:

Mission Street (Between Beale and Second Streets): There will be underground utilities work and traffic lane closures daily, Monday through Friday between 9:00 AM and 3:00 PM.

What to Expect Next Weekend (4/6/13 – 4/7/13):

FULL STREET CLOSURE - BEALE STREET BRIDGE INSTALLATION: Friday, April 5, at 7:00 PM. No through traffic or pedestrians will be allowed on Beale, only local access will be permitted. Beale Street will reopen Monday, April 8, at 5:00 AM.

WEATHER CONTINGENCY DATE: If necessary, due to weather, the bridge installation will be moved to the following weekend, April 12-15.

Beale Street (Between Mission and Howard Streets): This weekend the Beale Street temporary bridge installation work will be performed. When Beale Street reopens Monday April 8, 2013, there will continue to be construction impacts with traffic lanes reduced from three down to two lanes until mid April 2013. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gates. The Beale Street temporary bridge requires closing of the east sidewalk between Mission Street and Howard Street until mid April 2013. Pedestrians are to use the west sidewalk and are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross.

Eastern Transit Center Site (Between Beale and Fremont Streets): This weekend there is no construction work scheduled for Saturday, April 6 or Sunday, April 7. However; dependent on contractor progress excavation and trucking may be performed Saturday April 6, between 7:00 AM and 7:00 PM. On Saturday night and Sunday the hours of operation and level of activity may be reduced. There may also be bridge preparation work. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gates onto Beale Street.

Central Transit Center Site (Between First and Fremont Streets): This weekend there is no construction work scheduled for Saturday, April 6 or Sunday, April 7. However; dependent on contractor progress excavation and trucking may be performed Saturday April 6 between 7:00 AM and 7:00 PM. On Saturday night and Sunday the hours of operation and level of activity may be reduced. Trucks will enter from the construction gate located at Fremont Street (between Mission and Howard Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Western Transit Center Site (Between Second and First Streets): This weekend there is no construction work scheduled for Saturday, April 6 or Sunday, April 7. However; dependent on contractor progress excavation and trucking may be performed Saturday April 6, between 7:00 AM and 7:00 PM. On Saturday night and Sunday the hours of operation and level of activity may be reduced. Trucks will enter from the construction gate located on Howard Street (between First and Second Streets) and exit the construction gate at First Street (between Mission and Howard Streets).

Detours, Street and Sidewalk Closures:

The following streets will be temporarily impacted due to project activities. So you can plan ahead, please review the affected streets below:

FULL STREET CLOSURE - BEALE STREET BRIDGE INSTALLATION: Friday, April 5, at 7:00 PM. No through traffic or pedestrians will be allowed on Beale, only local access will be permitted. Beale Street will reopen Monday, April 8, at 5:00 AM.

WEATHER CONTINGENCY DATE: If necessary, due to weather, the bridge installation will be moved to the following weekend, April 12-15.

Beale Street (Between Mission and Howard Streets): The Beale Street temporary bridge preparation has resulted in construction impacts with traffic with lanes reduced from three lanes down to two lanes until mid April 2013. The Beale Street temporary bridge work requires closing of the east sidewalk between Mission Street and Howard Street until mid April 2013. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gates. Construction flaggers and SFPD 10B Officers will be assigned during peak hours to assist with traffic and pedestrians. Pedestrians are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross.

BEALE STREET BRIDGE NOTE: The Beale Street Temporary Traffic Bridge (between Mission and Howard Streets) is scheduled to be completed April 8, 2013. When Beale Street reopens there will continue to be construction impacts to traffic lanes reduced from three down to two lanes until mid-April. Beale Street traffic may also be impacted occasionally during construction with trucks exiting at the construction gates. The Beale Street temporary bridge requires closing of the east sidewalk between Mission Street and Howard Street until mid April 2013. Pedestrians are to use the west sidewalk and are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross.

Fremont Street (Between Mission and Howard Streets): Fremont Street traffic may be impacted occasionally during construction with trucks entering and exiting at the construction gates. Construction flaggers and SFPD 10B Officers will be assigned during peak hours to assist with traffic and pedestrians. Pedestrians will continue to use west sidewalk of the temporary bridge between Mission and Howard Streets. Pedestrians are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross. NOTE: The Fremont Street temporary bridge traffic signal will be activated mid block between Mission and Howard Streets at the First Street Bridge and construction access trestle intersection in March or April 2013.

First Street (Between Mission and Howard Streets): First Street traffic may be impacted occasionally during construction with trucks entering and exiting construction gates. Construction flaggers and SFPD 10B Officers will be assigned during peak hours to assist with traffic and pedestrians. Pedestrians will continue to use west sidewalk of the temporary bridge between Mission and Howard Streets. Pedestrians are urged to please use the crosswalks at the Mission and Howard Street intersection to safely cross.

Natoma Street (Between Fremont and First Streets): Natoma Street (between Fremont and First Streets) has been reduced to one lane, one way (west bound), all vehicles will enter from Fremont Street and exit at First Street. Local vehicle and pedestrian access will remain available.

Natoma Street (Between First and Second Streets): Natoma Street (between First and Second Streets) has been changed to a dead end street for the life of the project with no vehicle access through Natoma Street from Second Street. Local vehicle and pedestrian access will remain available.

Minna Street (Between First and Second Streets): Minna Street has been reduced to one lane, one way (west bound), all vehicles will enter from First Street and exit at Second Street. There will be no parking along Minna Street between First Street and 130 feet east of Second Street for the life of the project. Local vehicle and pedestrian access will remain available.

Mission Street (Between First and Second Streets): There will be underground utilities work and traffic lane closure daily, Monday through Friday between 9:00 AM and 3:00 PM.

Howard Street (Between Fremont and Second Streets): Howard Street traffic may be impacted occasionally during construction with trucks entering and exiting the construction gate at Howard Street (between First and Second Streets). Construction flaggers will be assigned during peak hours to assist with traffic and pedestrians.

Community Meeting

Excavation of the Transbay Transit Center site is now in full swing and contractors are preparing to install the third and final traffic bridge on the weekend of April 5-8. All around the jobsite, we are bustling with activity and would like to invite you to come to our next community meeting to see what exciting things are currently taking place. Join us on Wednesday, April 3, 2013 to learn more about construction activities, the final temporary bridge installation, mass excavation and internal bracing, street closures, and the hours of activity. The community meeting will be held from 12:00 noon until 1:00 PM at the TJPA’s offices located at 201 Mission Street, Suite 2100. We appreciate that you are taking your lunch hour to learn more about this innovative project, and would of course welcome you to bring food or drinks to this meeting.

What: Community Meeting: Transbay Construction Update

When: Wednesday, April 3, 2013

Time: 12:00 Noon

Where: Transbay Joint Powers Authority 201 Mission Street, Suite 2100 San Francisco, CA 94105

The Transbay Archaeology Exhibit

On Friday, March 29, the Transbay Archaeology Exhibit is returning to its original location in the lobby of 201 Mission Street (corner of Mission Street and Beale Street). The exhibit will be open during regular business hours from 9:00 AM - 5:00 PM and will be on display through the end of June.

Stay tuned.

Comments

Popular posts from this blog

Alex Castro, Electronic Arts VP, Is Oakland’s “Fake Joe Tuman”, “Crocker Mom”

Alex Castro, is currently Vice President Of Product Management At Electronic Arts, and a fairly-well-known and legendary tech executive, regularly quoted in a number of industry publications. But Alex Castro’s also an Oakland resident who has the terrible habit of going online, making traceble email accounts from his Electronic Arts office, and posing as someone […] from WordPress http://ift.tt/1fVkWP9 via IFTTT

Event: Jog For Jill San Francisco Run September 12th Golden Gate Park

Cal Women's Rowing Team member Jill Costello passed away from complications due to lung cancer on June 24th 2010 and at the age of 21. A San Francisco event and run called Jog For Jill has been established and will be held this Sunday, September 12th at 5 PM. Two members of the Cal Women's Crew team were at the Cal vs. Davis football game wearing Jog For Jill shirts, and were kind enough to provide the video interview above. Below are the other details from the event website, where you're encouraged to pre-register here CLICK FOR SITE : Pre-Registration: Online/$25 Day of Registration: 4:00 p.m./$30 Shotgun Start: 5:00 p.m. After run/walk celebration: 6:00 p.m.- 8:30 p.m. Event Location: Golden Gate Park Music Concourse Bandshell S Tea Garden Drive San Francisco, California 94118 Participants are encouraged to pre-register. Only pre-registered participants will be guaranteed a walk/run T-shirt. T-shirts will be limited to the first 2500 day of regis...

Interview: Imani, Chef Owner of Roasted and Raw RoastedRaw.com, For Oakland Restaurant Week 2023

Interview: Imani, Chef Owner of Roasted and Raw RoastedRaw.com, For Oakland Restaurant Week 2023 Interview: Imani, Chef Owner of Roasted and Raw RoastedRaw.com, For Oakland Restaurant Week 2023. Imani Greer gets a highlight in The Oakland Post: Chef Imani Greer, a culinary entrepreneur, has created quite a stir — and menu — for the Bay Area’s vegan-loving community with the opening of his new Roasted and Raw (R&R) restaurant near Oakland’s Jack London Square. I am proud to welcome him to Zennie62Media for Oakland Restaurant Week 2023. Stay tuned. via YouTube https://www.youtube.com/watch?v=8QvMqVWLAH4